• Project Name

    Radiant Furnace Replacement

  • Client

    Zinc and lead smelting and refining complex

  • Location

    Trail, BC

  • Project Duration

    January 2024 – April 2024

  • Contract Value

    Not specified

  • Project Type

    Capital

Radiant Furnace Replacement

Scope Highlights

Project Objectives

 

Extend the operational life of the waste heat boiler and ensure continued safe and efficient performance through full demolition and replacement of the radiant boiler section.

Technical Challenges

  • Execution of full boiler replacement in a turnaround schedule
  • Managing corrosion resistance requirements
  • Coordinating multiple subcontractors and heavy lifts

Unique Solutions

  • Use of ERNiCrMo-14 (Alloy 686) for corrosion-resistant overlay
  • Custom Inspection and Test Plans (ITPs)
  • Specialized welder qualifications and tailored welding procedures
  • Comprehensive multi-stage testing

Performance Metrics

Trades Involved

Boilermakers, Pipefitters, Ironworkers, Millwrights, Laborers

 
Subcontractors

ACUREN Group, Steel Wings Insulators, GWIL Crane / Sterling Crane,Kodiak Measuring,Kootenay Technical Surveyors, Hil-Tech Contracting, Clean Harbors

Key Takeaways

Completed under the 2024 Turnaround Plan with high safety and quality standards.

Use of Alloy 686 and rigorous testing ensured long-term durability.

Collaboration among subcontractors and adherence to environmental and safety protocols contributed to project success.

Project Successfully Completed ✓