• Project Name

    Sulphur Rail Car Dumper Replacement

  • Client

    Marine Terminal

  • Location

    North Vancouver, British Columbia

  • Project Duration

    January 6 – April 30, 2025

  • Contract Value

    Not specified

  • Project Type

    Industrial Infrastructure Replacement

Terminal Sulphur Rail Car Dumper Replacement

Scope Highlights

Project Objectives

 

Replace the aging rotary sulphur dumper system to ensure continued operational integrity and regulatory compliance.

Technical Challenges

  • Coordination with concurrent Sulphur Dumper Building Replacement project
  • Execution in a live brownfield environment
  • Tight schedule
  • Constrained port environment
  • Wind speed monitoring for crane operations
  • Alignment with ship schedules
  • Delays due to manufacturing quality issues

Unique Solutions

  • Close collaboration with third-party contractors
  • Use of 715-ton cranes for heavy lifts
  • Workflow reorganization to maintain productivity
  • Adherence to safety and quality protocols

Performance Metrics

Trades Involved

Ironworkers, Pipefitters, Millwrights, Operating Engineers, Painters

 
Subcontractors

ISSL (scaffolding), Gwil Crane, ACL Crane, Kodiak Measurements, Ross Rex, Acuren

Key Takeaways

Project completed with no recordable safety incidents.

Strong adherence to clients HSE program.

All QA/QC activities met regulatory standards.

Substantial completion achieved with full documentation and commissioning support.

Successful coordination and execution in a constrained environment.

Project Successfully Completed ✓