• Project Name

    Waste Water Treatment Project

  • Client

    Nova Chemicals

  • Location

    Corunna, Ontario

  • Project Duration

    10 Months

  • Contract Value

    $6M

  • Project Type

    Capital

Waste Water Treatment Project

Scope Highlights

Project Objectives

 

Implement a new water treatment unit to pre-treat wastewater generated by operations, minimizing environmental impact and ensuring regulatory compliance.

Technical Challenge

 

Demolition and reconstruction of a 20-foot-deep concrete basin that had not been touched in 50 years, requiring careful planning and heavy equipment.

Unique Solutions

 

Used structural steel support system to reduce exposure time and eliminate the need for shoring scaffolding, expediting delivery timeline.

Performance Metrics

Trades Involved

Labours Local 1089, Carpenters Local 1256, Operating Engineers Local 793, IBEW 530, Ironworkers Local 700

 
Trade Discipline

Civil Construction

Key Takeaways

CIMS successfully executed the project with a focus on safety and quality.

Heavy demolition was completed in a constrained environment with no major incidents.

Planning and innovation led to efficient delivery and minimized workforce exposure.

Project Successfully Completed ✓